Data centers in Arapahoe County, CO
Everything on file with the regulator, added up. Every figure links to the filing it came from.
5 permitted facilities.
These facilities hold active air permits in EPA's national registry. Groundwork has not yet read CO's permit documents, so generator counts and permitted emissions show as pending here — unlike Virginia, where every figure is read from the permit itself.
What this does — and doesn't — mean.
These are emergency backup generators. They are permitted to run during grid outages and for routine testing — typically tens of hours a year, not continuously. A permit is a ceiling on what a site may emit, not a measurement of what it does emit.
A permit also is not a building. An issued permit establishes approval; it does not establish that anything is built, energised or running.
None of the 5 sites here that Groundwork could locate sits in a FEMA Special Flood Hazard Area.
No single permit discloses the total permitted in this county. That number exists only because 5 separately-published filings were added together. Each one, read alone, looks routine.
Every tracked site in Arapahoe County.
| Site | Operator | Permits | Generators | NOx t/yr | Flood zone |
|---|---|---|---|---|---|
| AMAZON DATA SERVICES - DEN-22 | Amazon | — | — | — | Zone X |
| NISSAN N. AMERICA - NISSAN DATA CENTER | — | — | — | — | Zone X |
| QTS AURORA LLC - QTS DEN1 | QTS | — | — | — | Zone X |
| EQUINIX LLC - EQUINIX LLC DE1 | Equinix | — | — | — | Zone X |
| DATABANK - DEN2 AND DEN5 | DataBank | — | — | — | Zone X |
4 operators of record · 5 of 5 located sites draw from a basin WRI rates high or extremely high for water stress.
Groundwork has this state’s facilities from EPA’s national air-permit registry, but has not yet read the state’s own permit documents. Generator counts and permitted emissions therefore show as pending.
Spotted an error?
Fuzzy-matched fields are labelled as such and some will be wrong. Open an issue — corrections are tracked in public and noted on the page.